Our extension was generously funded by Grants from these three donors.
A Virtual Tour of the Club House Extension and outdoor areas
Club House extension Weekly Progress photos.
Members helped to make the extension into a Club House over a couple of months
into 2020 and then Corvid 19 struck and we did not open.
Final touches !
Fitting out the extension began in January. The floor was laid over 10th - 13th February. Fitting the building for use continued with new notice boards, the toilet 's fitments, and buying heaters,new chairs, disability ramp,and the can crusher.
Week 13. Kitchen complete. General fitting out. Extract Fan, and pathways and to Completion Day 2 of Week 14, December 3rd 2019
Week 12. Kitchen fitting, UPVC outdoor wall cladding, Internal painting
Week 11; to 17th November; Kitchen fittings, final plastering, painting. New LED light fittings throughout.
Week 10 - ending 8th November:
All toilet floors; Gents WC fittings & decorations. Kitchen walls plastered. Wiring continued.
All toilet floors; Gents WC fittings & decorations. Kitchen walls plastered. Wiring continued.
Week 9 to November 1st
First fix for electrics; Plaster Board over steel beam and stanchions and the walls. Hatch door.
Week 8. Final sealing of the roof. Glass roof lights fitted and inside fitting out commenced.
Week Seven. Internal details. Roof light support wells constructed. Roof membrane nearly complete
Week Six. New timber roof , with roof light apertures Fire protective paint to steel work
Week 5, by October 5th New club room, store and new toilets take shape. Old outside wall removed.
Week 4. Timber frame walls, insulation, and new drain completed.
Week 3. Shuttering, steel reinforcement and concrete pouring with 3 loads - mixed on site.
and end of week 4.
and end of week 4.
Week 3. Foundations with broken hard core, and sand
Week 2; Breaking old foundations of 1970's buildings and excavate for foundations. Boards for the greenkeeper's mower.